Case Study: Heat Treatment Project for OEM Customer

Location: Atlantic Terminal, Baltimore, MD

Date: September 2022

Project Facts

Project Scope

  • Heat treatment facility for vehicle export to Australia and New Zealand

Facility Size

  • 2 metal buildings, 60×120 sq. ft. each

Process Overview

  • Total time: 1.5 to 2 hours, including heat-up and cool-down
  • 30-minute heating period maintaining 133°F using remote sensors
  • Capacity: Approximately 48 cars processed per cycle (24 per building, depending on vehicle size)

Operational Partners

  • Orkin pest control operators

Key Equipment

  • Insulated steel buildings with plug-in fans for heat circulation
  • Remote thermostats monitored from a nearby trailer
  • Propane heaters with hose setups for 6 heaters per building

The Problem

In 2022 one OEM customer faced a significant challenge: Australia and New Zealand had implemented stringent biosecurity regulations requiring all vehicles exported to these markets to undergo heat treatment. This was a novel regulatory mandate, and the customer’s existing export processes did not meet the requirements.

The OEM turned to Amports with the urgent problem: How to meet the new export standards and avoid disruption to their global supply chain?

Amports was the first to implement a heat treatment solution, setting a global standard.

An external view of Amports heat treatment building
Amports was the first to implement a heat treatment solution, setting a global standard

The Solution

Amports engineers and logistics experts devised an innovative solution that not only addressed the regulatory requirements but also set a precedent for the automotive export industry.

Initial Approach and Challenges

  • Proposal 1. Build a temporary shelter using A-10 tarpaulin
  • Outcome. The fabric failed to retain heat effectively.
  • Challenge Identified. Heat loss and inability to maintain consistent temperature were critical issues
  • The Winning Approach. Permanent Metal Structures

Design and Build

  • Opted for insulated steel buildings to ensure efficient heat retention
  • Spray insulation applied to minimize heat loss and maintain consistent temperatures
  • Due to permitting constraints the team designed two smaller buildings instead of one larger structure to streamline approval and construction

Engineering Features

  • Installed plug-in fans for even heat distribution
  • Equipped buildings with remote monitoring systems, allowing Orkin operators to track temperatures from a nearby trailer
  • Integrated propane heaters with enough hoses to power six heaters per building, ensuring rapid and uniform heat-up

Process Implementation

  • Vehicles were loaded into the buildings and subjected to a 30-minute heat treatment at 133°F, monitored by advanced sensors
  • After treatment, vehicles cooled and were prepared for export

The Results

  • The OEM customer successfully exported treated vehicles to Australia and New Zealand, meeting stringent biosecurity standards
  • Amports’ solution became an industry benchmark, with heat treatment now being a standard practice worldwide
  • The project demonstrated Amports’ creativity, technical expertise and collaborative problem-solving approach
An internal view of Amports heat treatment building
From concept to execution Amports demonstrated its ability to think outside the box and deliver results
Share this post